CMC Modifications Workshop 36 Timetable
Four proposed Modifications to the Capacity Market Code have been submitted for consideration at Workshop 36. This timetable is related to the following modifications:
CMC_02_24: Modification to the performance security requirement
CMC_03_24: Enduring mechanism for indexation based on GB model
CMC_04_24: Recovery of Net Present Value lost as a result no-fault delays to new capacity projects
CMC_05_24: Amendment to J.6.1.6 to recognise extensions granted under SEM-23-101 and SEM-23-108
The RAs are today, 05 April 2024, publishing the timetable setting out how they plan to consult and make a decision relating to the proposals.
As set out in the timetable, the RAs intend to consult on the modifications from Friday 19 April 2024 to Monday 20 May 2024, for a period of 5 weeks and intend to publish their decision by Friday 28th of June 2024.